NAMIBIA: Mokuti Etosha

LOCATION: Etosha

WHAT DID THE PROJECT ENTAIL? Renovations included new public areas on the lodge, reception, conferencing facilities, swimming pool area, a new boma as well as upgraded rooms.

HOW LONG DID THE PROJECT TAKE? 12 months

HOW MUCH CEMENT WAS USED? 2321.38m³

PROJECT STATISTICS: 
Brick Steps = 133.38m²
110mm walls = 934.21m²
220mm walls = 6837.08m²
330mm walls = 428.11m²
440mm walls = 147.59m²
660mm walls = 24.20m²

Plaster m²
Internal walls
= 5449.24m²
External walls = 2665.51m²
Bagged walls = 2280.34.24m²
Screeds = 2121.37m²

Project information and photos provided by Nexus Construction.

CONTRACTOR: Nexus Building Contractors (Pty) Ltd

 